Park Bond

Voters pass park bond referendum

On November 6, 2018, Brooklyn Park voters passed a park bond referendum with 63% of the vote. Now, the City will continue to seek feedback from the community on refining the specifics for each project.

Projects

The following projects will be implemented:

Park Priority Cost

Natural resources

  • Develop and implement a Natural Resource Management plan to include removing invasive species, correcting and stabilizing river/creek shoreline erosion, and managing tree and prairie restoration.  
$500,000

Trails, signs and lights

  • Construct trails to eliminate gaps in current trail system.
  • Develop and implement a sign system to help people get to where they want to go on local trails.
  • Install trail lighting to improve safety. 
$2,400,000

Park reinvestments

  • Redevelop neighborhood parks, including but not limited to Lakeland, Hartkopf and Norwood Park.
  • Renovate park buildings used for recreation programs, including but not limited to Willowstone, Monroe and Northwoods parks.
  • Add kitchen facilities at River and Central park shelters.
  • Construct large capacity picnic shelter(s) within the park system.
$13,100,000
Community Activity Center and Senior Center
  • Renovate Community Activity Center to improve customer service and experience.
  • Make customer service desk and program space ADA compliant.
  • Renovate the front entrance, improve senior facilities and upgraded restrooms.
  • Designate program space specifically for senior fitness and activities, and adult programs.
$4,000,000

Fields and courts

  • Develop a hometown ballfield with a grandstand, restrooms and concession areas.
  • Partner with Park Center High School to install lighting on new turf fields.
  • Redevelop multi-use field space to increase space for soccer, lacrosse and cricket.
$2,600,000

Teen Center

  • Develop an additional Teen/Recreation Center to serve youth (location to be determined). 
$2,000,000
Historic Eidem Farm
  • Develop and implement the Self-directed Interpretative Site Plan.
  • Construct a building to provide restrooms, classroom space and offices to improve the customer experience and expand programming opportunities. 
$1,400,000
Total $26,000,000

 

Community feedback

While the Park System Plan provides the roadmap to these park projects, the neighborhoods and the community at-large will provide additional input and feedback on specific park redevelopment.

Learn more

Keep up with these and other park projects within the Park System Plan.

Visit Park System Plan

Contact us

Community Activity Center (Recreation and Parks Department)

5600 85th Ave. N.
Brooklyn Park, MN 55443
View map and directions to the Community Activity Center

Holiday hours

We are closed Friday, November 23 for Thanksgiving.

September through May office hours

Sunday through Saturday, 8 a.m. to 10:30 p.m.

June through August office hours

Monday through Thursday, 8 a.m. to 10:30 p.m.
Friday, 8 a.m. to 5 p.m.
Saturday and Sunday, closed unless we have a scheduled event or activity.

Hours may vary based on events, activities and holidays.

Phone and email

Tanya Moore
763-493-8367
Email Tanya Moore

 
close (X)